2.10.2025

Fingrid extends restrictions on new energy storage facility connections in Southern Finland until 2029

Finland is currently experiencing an unprecedented interest in the construction of grid energy storage facilities. With more than 30 GW of new requests for storage connection, preventative restrictions have been placed on new connections due to the shortage in available grid connection capacity. All storage projects in Finland above 5 MW must from now on submit a connection contract inquiry to Fingrid. Fingrid will then determine the maximum capacity available at each connection point, aiming to balance local consumption and production growth. 

Key takeaways:

  • No new large-scale storage (> 5 MW) in the south before 2029 (until the completion of the Hikiä–Toivila grid expansion)
  • Developers should consider Central or Northern Finland, where capacity is still available.
  • Fingrid is considering piloting flexible connection models to allow earlier access in constrained areas, as currently considered in Fingrid’s draft main grid development plan for 2026–2035.

For investors and developers, this means:

  • Location strategy is now critical.
  • Maintaining an open dialogue with Fingrid throughout the whole project development phase is important to keep track of the capacity situation.
  • Financing risk arises where timelines depend on future grid expansions.

This is a timely reminder that proactive legal strategy is just as critical as the technology itself for project success. Castrén & Snellman is closely following the development of the electricity transmission sector and is advising clients on how to navigate Finland’s energy transition.

Latest references

We advised Neoen Renewables Finland Oy, part of the French Neoen Group, in its sale of a data centre project to a consortium consisting of international data centre developers and operators. This marked Neoen’s first data centre development project in Finland. Founded in 2008, Neoen is one of the world’s leading independent renewable energy producers. The company operates in 15 countries. It develops, finances, builds, owns, and operates solar power plants, wind farms, and battery storage systems. Neoen Group is owned by global alternative asset manager Brookfield Corporation.
Case published 17.9.2026
We acted as Finnish law legal adviser to the lenders and the export credit agencies in connection with the EUR 514.4 million green project financing for the development and construction of Easpring Finland New Materials Oy’s cathode active material (CAM) manufacturing plant in Kotka, Finland. The borrower, Easpring Finland New Materials Oy, is a joint venture owned by Beijing Easpring Material Technology, Finnish Minerals Group and LG Energy Solution. The financing was provided by six international commercial banks, with Société Générale acting as financial adviser and mandated lead arranger together with Natixis as co-mandated lead arranger, and DNB, ICBC, ING and Standard Chartered participating as lenders, with support from the export credit agencies Finnvera and Sinosure. The project represents a significant milestone for Finland and the European battery value chain by strengthening Europe’s domestic supply of cathode active materials, a key component in lithium-ion batteries for electric vehicles and energy storage applications. Once the first phase of the project is operational, the Kotka facility is expected to produce approximately 60,000 tonnes of cathode active material annually, making it one of the largest CAM production plants in Europe and supplying leading battery manufacturers across Europe. 
Case published 21.7.2026
We acted as Finnish legal advisor to Delta Capacity in connection with its acquisition of the ready-to-build Karppio battery energy storage system (BESS) project from Helios Nordic Energy. The acquisition was made and the project will be implemented together with Strioga Family Foundation. The Karppio BESS project is located in Teuva, Finland, and has a capacity of 125 MW / 300 MWh. Delta Capacity will lead the remaining development of the project through to commissioning, planned for 2027, and will serve as long-term asset manager. Delta Capacity is a Swiss-based developer of utility scale battery storage systems. The acquisition adds to Delta Capacity’s growing Nordic portfolio. 
Case published 20.7.2026
We advise Winda Energy Oy on the development of its c. 100 MW data centre project in Janakkala, Finland, a landmark investment exceeding EUR 500 million. The project is being developed in collaboration with European investment company Gi21 Capital. Construction is scheduled to commence in 2027, with completion targeted for 2028. Winda Energy Oy is a renewable energy project development company established in 2011, with a portfolio of wind and solar power projects across Finland. The company manages projects throughout their full lifecycle, from initial planning and permitting to construction and completion. 
Case published 8.7.2026