3.6.2022

Plan to speed up green transition investing by providing temporary priority processing and expedited appeals – statements can be issued

The Ministry of the Environment is preparing amendments that will temporarily allow priority processing of certain permit applications in Regional State Administrative Agencies. This priority processing would concern permits for investments that support the green transition under the Environmental Protection Act (527/2014) and the Water Act (587/2011). In addition, administrative courts would handle appeals concerning projects and town plans central to the green transition as urgent. These expedited proceedings would be in effect during 2023–2027.

The goal of the amendments is to promote the green transition and the investments it requires by speeding up the processing of related permit applications and appeals. 

Priority permit procedures

If a project promotes the green transition, related permit applications under the Environmental Protection Act and the Water Act would, at the applicant’s request, receive priority processing at the Regional State Administrative Agency, which means they would be processed faster.

The legislation would include a comprehensive list of the projects that would be eligible for prioritising over other permit applications under the Environmental Protection Act and the Water Act. Eligible projects would include projects concerning renewable energy and electrification of industry, manufacturing and utilising hydrogen, capturing, utilising and storing carbon dioxide, battery plants, and manufacturing, reusing and recycling battery materials. 

Another prerequisite for priority processing would be that the applicant can sufficiently demonstrate that the operation takes into account the principle of ‘Do No Significant Harm’ (DNSH). The applicant needs to provide a written assessment of any significant risks to the environmental objectives of the EU Taxonomy Regulation ((EU) 2020/852) caused by the project (a so-called DNSH assessment). These objectives are climate change mitigation, climate change adaptation, the sustainable use and protection of water and marine resources, the transition to a circular economy, pollution prevention and control, and the protection and restoration of biodiversity and ecosystems. The reason for this assessment requirement is that priority processing is meant to be an incentive for realising investments that account for the DNSH principle.

However, the Ministry of the Environment’s proposal does not clearly state how, on the one hand, applicants should demonstrate compliance with the DNSH principle and, on the other hand, the authorities should verify this compliance. First of all, the proposal refers to the environmental objectives of the Taxonomy Regulation but does not make a reference to the regulation’s DNSH assessment. According to the reasoning, however, this assessment would be applied and the assessment criteria would correspond with the general DNSH assessment criteria of the Taxonomy Regulation. The proposal does not make a direct reference to the delegated regulations supplementing the Taxonomy Regulation that lay down the technical screening criteria. Second, applicants could also make use of the assessment for financing applications under the Union’s Recovery and Resilience Facility (RRF) if it can sufficiently demonstrate that the project takes the DNSH principle into account. The DNSH principle is based on the Taxonomy Regulation for RRF as well, but the European Commission has provided separate technical screening criteria for applying the DNSH principle for RRF. The Finnish Environment Institute has drafted a separate guidance on implementing the DNSH principle for measures under the Finnish recovery and resilience plan. Clarifying the proposal in terms of the applicable screening criteria would help both the applicants and the authorities. Unless this is done, there is a risk that the ambiguous screening criteria will create undue administrative burden for the applicants and lengthen the processing times, defeating the purpose of the amendments – the advancement of the green transition.

According to the proposal, in practice, the Regional State Administrative Agency would notify the applicant on its decision to prioritise the application’s processing. The applicant would not have the option to appeal this priority decision, and it could only be appealed in connection with the permit decision of the principal matter. Appealing the priority decision only after the matter is processed cannot be deemed efficient. In this respect, the proposal refers to the applicant’s option to re-request priority processing and to supplement the DNSH assessment during the procedure.

Regional State Administrative Agencies would implement priority processing as of the entry into force of the amendments until the end of 2025. Applicants could also request priority processing for permit matters that are already pending when the amended Act enters into force.

Handling appeals as urgent in administrative courts

Administrative courts would, by virtue of office, handle as urgent any appeals that concern expedited permit decisions under the Environmental Protection Act and the Water Act and that received priority processing by the Regional State Administrative Agency. This would ensure that permit matters would be treated as a matter of urgency both during permit processing and in connection with any appeals, thus speeding up the overall process. However, the proposal does not address how the administrative courts would account for the right to appeal the Regional State Administrative Agency’s decision on priority processing.

The amendment being drafted would also include new provisions to the Land Use and Building Act (132/1999) concerning appeals on town plans considered significant for the production of renewable energy and local master plans guiding the construction of wind power.  Administrative courts would handle these appeals as urgent.

The urgent handling of applicable appeals would be in effect in administrative courts as of the entry into force of the amendments until the end of 2027.

Statements to the amendments can be issued

Statements to the amendments under preparation can be issued until Tuesday 7 June 2022.

The amendments are scheduled to enter into force on 1 January 2023.

Authors: Matias Wallgren, Sanna-Mari Seppälä, Kanerva Sunila and Laura Aitala

Latest references

We advised Neoen Renewables Finland Oy, part of the French Neoen Group, in its sale of a data centre project to a consortium consisting of international data centre developers and operators. This marked Neoen’s first data centre development project in Finland. Founded in 2008, Neoen is one of the world’s leading independent renewable energy producers. The company operates in 15 countries. It develops, finances, builds, owns, and operates solar power plants, wind farms, and battery storage systems. Neoen Group is owned by global alternative asset manager Brookfield Corporation.
Case published 17.9.2026
We acted as Finnish law legal adviser to the lenders and the export credit agencies in connection with the EUR 514.4 million green project financing for the development and construction of Easpring Finland New Materials Oy’s cathode active material (CAM) manufacturing plant in Kotka, Finland. The borrower, Easpring Finland New Materials Oy, is a joint venture owned by Beijing Easpring Material Technology, Finnish Minerals Group and LG Energy Solution. The financing was provided by six international commercial banks, with Société Générale acting as financial adviser and mandated lead arranger together with Natixis as co-mandated lead arranger, and DNB, ICBC, ING and Standard Chartered participating as lenders, with support from the export credit agencies Finnvera and Sinosure. The project represents a significant milestone for Finland and the European battery value chain by strengthening Europe’s domestic supply of cathode active materials, a key component in lithium-ion batteries for electric vehicles and energy storage applications. Once the first phase of the project is operational, the Kotka facility is expected to produce approximately 60,000 tonnes of cathode active material annually, making it one of the largest CAM production plants in Europe and supplying leading battery manufacturers across Europe. 
Case published 21.7.2026
We acted as Finnish legal advisor to Delta Capacity in connection with its acquisition of the ready-to-build Karppio battery energy storage system (BESS) project from Helios Nordic Energy. The acquisition was made and the project will be implemented together with Strioga Family Foundation. The Karppio BESS project is located in Teuva, Finland, and has a capacity of 125 MW / 300 MWh. Delta Capacity will lead the remaining development of the project through to commissioning, planned for 2027, and will serve as long-term asset manager. Delta Capacity is a Swiss-based developer of utility scale battery storage systems. The acquisition adds to Delta Capacity’s growing Nordic portfolio. 
Case published 20.7.2026
We advise Winda Energy Oy on the development of its c. 100 MW data centre project in Janakkala, Finland, a landmark investment exceeding EUR 500 million. The project is being developed in collaboration with European investment company Gi21 Capital. Construction is scheduled to commence in 2027, with completion targeted for 2028. Winda Energy Oy is a renewable energy project development company established in 2011, with a portfolio of wind and solar power projects across Finland. The company manages projects throughout their full lifecycle, from initial planning and permitting to construction and completion. 
Case published 8.7.2026