2.2.2024

Solar and wind power projects affected by amendments to the Act on Expropriation Permits

Parliament has passed amendments to the so-called Act on Expropriation Permits (768/2004). The amendments, which enter into force in the beginning of February 2024, affect the expropriation permit process for overhead electrical power lines and transmission pipelines that are included in wind and solar power projects requiring an environmental impact assessment procedure (‘EIA procedure’).

The purpose of the amendments is to supplement the implementation of Directive 2011/92/EU on the assessment of the effects of certain public and private projects on the environment (‘EIA Directive’).

In the future, an expropriation permit is needed for all power lines and transmission pipelines included in projects requiring an EIA procedure

As a result of the amendments, all overhead electrical power lines and all types of transmission pipelines used for transporting gas, oil or chemicals require an expropriation permit if the power line or transmission pipeline is part of a project that is subject to an EIA procedure. This means that an expropriation permit is required, for example, in a situation where the connection lines of wind or solar power farms would not be subject to an EIA procedure as an independent project but are essentially related to a wind or solar power project that falls within the scope of an EIA procedure.

Previously, an expropriation permit was required only for power lines and transmission pipelines that were subject to an EIA procedure under Annex I of the EIA Directive, as well as for power lines with the minimum voltage of 110 kilovolts and for cross-border pipelines if an EIA procedure was applied to the project on the basis of a case-specific EIA screening decision.

Furthermore, the expropriation permit process was previously not necessary if the implementation of the project was in all respects based on a legally binding land use plan under the Land Use and Building Act (132/1999) and this plan included an assessment on the project’s location and relation to other use of the area. The amendments removed this limitation, and in the future the expropriation permit process will also be applied to projects based on legally binding land use plans.

Special requirements for the consideration of an expropriation permit for power lines and pipelines are added to the Act

Section 4 of the Act on Expropriation Permits will provide for new special requirements for the consideration of an expropriation permit for a power line or transmission pipeline. These special requirements will supplement existing provisions on the consideration of an expropriation permit. If the requirements provided for in the section are not met, the expropriation permit cannot be granted. The government proposal states this would mainly apply to situations where a different route for the powerline or transmission pipeline would be clearly better.

The section states that a power line or a gas pipeline has to be constructed in a technically and financially feasible manner in such a way that the adverse effects on the environment and on the use of the areas remain as small as possible. Construction cannot cause anyone more loss or inconvenience than is necessary.

The section also provides for the protection of the Sámi culture: ‘A project that is located in or impacts the Sámi homeland or Skolt area cannot materially impair the right of the Sámi to maintain and develop their culture and practise traditional livelihoods and the living conditions of the Skolt or the ability to practise the natural sources of livelihood referred to in the Skolt Act (253/1995) within the Skolt area.’

In an area where a regional plan or legally binding local master plan is in force, the construction of a power line or a transmission pipeline cannot hinder the use of the area for the purpose determined in the plan.

The local detailed plan must also be taken into account when constructing a power line or a transmission pipeline. The Economy Committee report on the government proposal states that the regulation should not prevent or delay projects that are significant for the clean energy transition if the project would only have minor impacts on the implementation of the local detailed plan. According to the report, the provision makes it possible, for example, to place a power line route irrespective of the land reservation entries and regulations in the local detailed plan, provided that the construction will not prevent the implementation of the essential principles and purpose of the plan.

In the future, the expropriation permit decision must include necessary regulations to restrict the significant adverse effects caused by the project

The EIA Directive requires that it is possible to issue permit regulations with respect to the environment in projects that fall within the scope of an EIA procedure.

After the amendments have entered into force, an expropriation permit decision must include necessary regulations regarding the power line or pipeline routing, project timeline and implementation methods as well as regulations regarding the observation of the effects of the project in order to restrict the significant adverse effects caused by the project. According to the government proposal, it is possible, for example, to make small changes to the power line route, but it is not possible to move the route to a completely different location.

The amendments’ impact on clean energy transition projects

Due to the amendments, it is possible that the number of cases handled in an expropriation permit process will increase and that the processes last longer if sufficient staff resources are not allocated to them. Moreover, the number of appeals concerning expropriation permits may also increase and the legal issues dealt within the appeals may become more complex.

Therefore, project developers should be prepared that the amendments can impact the timelines of individual projects. According to the government proposal, however, the amendments are not expected to delay the construction of electricity transmission lines required for the clean energy transition when considered as a whole.

In addition, the future will probably bring new changes to the expropriation permit process as the Parliament also approved a statement in connection with the aforementioned amendments in which it requires the government to draft a reform of the Act on the Redemption of Immovable Property and Special Rights (603/1977) for the Parliament without delay. The purpose of the reform is to strengthen the protection of property with, for example, increasing the amount of the expropriation compensation, as the clean energy transition causes significant land use needs regarding energy infrastructure.

Latest references

We advised KoBold Metals on the Finnish legal and tax aspects related to its earn-in agreement with Aurion Resources. Under the agreement, KoBold (through its wholly owned subsidiary KoBold Exploration Finland Oy) can earn an undivided 75% interest in commodities discovered (other than any discoveries that are predominantly gold or silver), by incurring USD 12 million in exploration expenditures on or before the fifth anniversary of the date of signing the agreement. The exploration area covers approximately 35 km2 in Aurion’s 100% owned 160 km2 Risti Property in Sodankylä, Finland Following satisfaction by KoBold of the earn-in requirements, a joint venture will be established with KoBold owning 75% and Aurion 25%. KoBold Metals Company is a US-based exploration and mining company, supported by high profile investors such as Breakthrough Energy Ventures, Andreessen Horowitz, and Equinor. It combines expertise in geosciences with artificial intelligence, machine learning, and data science to improve and accelerate the exploration process in search of the critical minerals necessary for the global energy transition.
Case published 26.3.2025
We are assisting Verne Global Ltd, the leading provider of sustainably powered HPC data centers in the Nordics, in developing a data center in Mäntsälä, Finland. We advised Verne in acquiring the real estate company managing the Mäntsälä site, as well as in the subsequent acquisition of the site itself. Our assistance extends beyond real estate transactions to include permitting and tax-related matters. Additionally, we advise Verne on grid connection and electricity supply matters. The acquisition of the project site in Mäntsälä marks Verne’s fourth data center in Finland, reinforcing its position as a leader in sustainable and scalable data center solutions. The Mäntsälä campus, spanning 10 hectares and located just a 40-minute drive from Helsinki-Vantaa International Airport, will initially offer a capacity of 70 MW. The facility is designed to support data-intensive enterprises and AI innovators running HPC, machine learning, and other high-intensity workloads, all while operating exclusively on renewable energy. Verne’s new facility will adhere to the company’s best practice design principles, focusing on maximizing efficiency and minimizing environmental impact. The campus will be powered entirely by renewable energy sources, and waste heat generated by the data center will be utilized for local community heating projects. The company is working closely with the Mäntsälä Municipality to ensure the new facility benefits the local area, including plans to harness waste heat for district heating. Construction of Verne’s Mäntsälä data center is set to begin in mid-2025 and is expected to take two years to complete. This expansion is a strategic move in Verne’s long-term plan to build out its sustainably powered data center platform, which was acquired by Ardian, a world-leading private investment house, in early 2024. Ardian has already invested over EUR 1.6 billion in the Nordics, focusing on energy transition and digital infrastructure projects, and is working with Verne to drive sustainable growth across the region.  Read Verne Global’s press release.
Case published 20.2.2025
We are assisting Verne Global Ltd, the leading provider of sustainably powered HPC data centers in the Nordics, in expanding a data center in Helsinki region, Finland. In the autumn of 2024, we acted as Verne’s advisor in acquiring the land at its existing Helsinki data center campus, securing room for future expansion. In addition to real estate development, our advice covers permitting and construction related legal matters. The expansion marks another milestone in Verne’s ambitious growth strategy for the Nordics, following the recent announcement of its new facility to be built in Mäntsälä, Finland. The land was acquired from Onvest, a family-owned company with a long history in the region. The site’s strategic location provides excellent connectivity to power and fibre networks, proximity to Helsinki Airport, and easy access to the city centre – making it ideal for organisations across industries looking for reliable, accessible, and well-connected facilities. Verne plans to develop the site further, leveraging its 70MW capacity to meet the increasing demand for sustainable, high-performance compute infrastructure. Designed with high-density compute in mind, the planned expansion will include two new buildings fully equipped to meet the technical requirements of AI, HPC, and other intensive workloads. Verne remains committed to sustainability, with the Helsinki campus running on 100% renewable energy. Waste heat generated by the data center is repurposed through a direct connection to the local district heating network. All new facilities will be built to support liquid cooling, enabling efficient management of the high heat levels generated by AI and other intensive compute workloads. Additionally, Verne uses renewable diesel for its backup power generators in Finland, reducing greenhouse gas emissions from the generators by an average of 90%. News: Verne expands Helsinki data center campus with strategic site acquisition. Read Verne Global’s press release.
Case published 20.2.2025
Castrén & Snellman is acting as the legal advisor to the City of Pori and Pori Energia Oy in the finance arrangement whereby debt facilities in the total amount of EUR 292 million are secured for the purpose of refinancing the existing liabilities and fuelling the future growth of Pori Energia. Pori Energia and its financiers signed a Finnish law governed facilities agreement for this purpose on 13 January 2025. Pori Energia, a multi-utility company, operates in various sectors including district heating, electricity distribution, and electricity generation through CHP and renewable sources. The company also provides wind power services and industrial energy solutions in the Satakunta region where it has c. 60,000 customers.
Case published 6.2.2025