27.6.2023

The Finnish State – The Court of Appeal dismissed the action of Peter Fryckman against the Finnish State

Related services

We successfully advised the Finnish State/the Ministry of Justice in a declaratory action in which the Helsinki Court of Appeal dismissed the claims of businessman Peter Fryckman and confirmed the non-existence of an arbitration agreement.

Fryckman had filed for arbitration before The Hague’s Permanent Court of Arbitration (PCA) in February 2018. The request was based on a claim that the Finnish Minister of Justice had signed a consent to arbitration between Fryckman and the Finnish State in the PCA.

The State denied the existence of an arbitration agreement in its response to the request for arbitration and refused to appoint its own arbitrator. The Secretary-General of the PCA deemed that the document titled ‘Declaration of Consent’ was too ambiguous and general in nature, and therefore he could not appoint an arbitrator for the State to an arbitration conducted under the PCA Arbitration Rules 2012.

After this, Fryckman requested that the District Court confirm the existence of an arbitration agreement between him and the Finnish State, under which disputes between the parties concerning tax and debt collection actions against Fryckman and his companies, as well as the resulting damages, would be settled before the Permanent Court of Arbitration in The Hague.  However, the District Court dismissed this action because the consent signed by the Minister of Justice was general in nature, its content was unspecified, and it was unclear whether the consent was even a matter that could be arbitrated. Furthermore, the District Court deemed that the consent signed by the Minister of Justice and the plaintiff’s application for commencement of arbitration were not identical and reciprocal, and there was no evidence of an agreement between the parties as to the commitment to and content of the agreement.

Fryckman appealed the District Court’s decision to the Court of Appeal, but in its judgement of December 2022, the Court of Appeal deemed that there was no cause to amend the District Court’s decision. The Court of Appeal found that the expression of will in the document titled ‘Declaration of Consent’ had not been made in accordance with the Ministry of Justice’s procedure for presentation and decision-making. According to the Court of Appeal, due to this key fault in the Ministry’s procedure, the free-form expression of will by the Minister did not have a binding effect on the parties. The Court of Appeal remarked that the plaintiff’s actions bore characteristics of an intent to bypass the Ministry’s customary procedure for decision-making. The Court of Appeal also noted that the Minister’s expression of will was encumbered by deficiencies in arbitrability and the subject matter of the consent as stated by the District Court, and referred to the grounds stated by the District Court in other respects as well.

On 5 May 2023, the Supreme Court ruled that no leave to appeal would be granted, and the judgment of the Court of Appeal is therefore final.

Latest references

We successfully represented Trety AB in a dispute and settlement negotiations concerning an agreement for development and production of communication devices for the healthcare sector. Eventually, the parties reached an amicable settlement to the full satisfaction of our client and thus the parties avoided an extensive arbitral proceeding. Trety AB is a global company that provides its customers with solutions for development, industrialization and production of electronics. Trety AB has over 30 years’ experience from IT, electronics and telecommunication industries.
Case published 11.2.2025
We successfully represented a Finnish manufacturing company in arbitration proceedings under the SCC rules against a global construction company. The dispute was governed by Finnish law and the seat of arbitration was Stockholm, Sweden. The dispute mainly concerned the termination of an erection contract and the right to compensation for delays of the project and for cost increases due to Russia’s invasion of Ukraine. The main questions in dispute were the lawfulness of the termination of the erection contract as well as the consequences of the termination such as the right to costs to complete the project after termination, the right to liquidated damages for delay of the project and adjustment of contract price due to cost increases. The total value of the dispute exceeded EUR 15 million.
Case published 8.1.2025
We represented a mutual real estate company belonging to a large Finnish group in arbitration proceedings against a construction company. The arbitral tribunal rejected the construction company’s claims in their entirety and ordered the construction company to reimburse our client for the costs of the arbitration proceedings in full. The dispute concerned the contract price under the construction contract, which was agreed to be determined on the basis of our client’s yield requirement and the rent under the lease agreement for the building in question. The parties disagreed on the indexation clause applicable to the rent adjustment and its impact on the contract price.
Case published 22.11.2024
We successfully represented a major Finnish construction company in a dispute and settlement negotiations concerning a large construction project. The dispute mainly concerned liabilities for additional and change works as well as project delays, and the value of the claims of the parties was approximately EUR 50 million.  If the case had not been settled, it would have been one of the largest construction disputes ever tried in the Finnish courts. The projected number of hearing days was unprecedentedly more than 300 days. To find an amicable solution to the extensive dispute, the parties engaged in settlement negotiations and court mediation. Eventually, the parties reached an amicable settlement to the full satisfaction of our client and thus the parties avoided the costs and risks of an extensive trial.
Case published 7.2.2024