18.7.2023

Global engineering and manufacturing company Contract dispute

Related services

We advise a global engineering and manufacturing company in a contract dispute. The dispute concerns the cancellations of several agreements relating to the procurement. The total value of the claims is close to EUR 400 million.

Latest references

We successfully represented Trety AB in a dispute and settlement negotiations concerning an agreement for development and production of communication devices for the healthcare sector. Eventually, the parties reached an amicable settlement to the full satisfaction of our client and thus the parties avoided an extensive arbitral proceeding. Trety AB is a global company that provides its customers with solutions for development, industrialization and production of electronics. Trety AB has over 30 years’ experience from IT, electronics and telecommunication industries.
Case published 11.2.2025
We successfully represented a Finnish manufacturing company in arbitration proceedings under the SCC rules against a global construction company. The dispute was governed by Finnish law and the seat of arbitration was Stockholm, Sweden. The dispute mainly concerned the termination of an erection contract and the right to compensation for delays of the project and for cost increases due to Russia’s invasion of Ukraine. The main questions in dispute were the lawfulness of the termination of the erection contract as well as the consequences of the termination such as the right to costs to complete the project after termination, the right to liquidated damages for delay of the project and adjustment of contract price due to cost increases. The total value of the dispute exceeded EUR 15 million.
Case published 8.1.2025
We represented a mutual real estate company belonging to a large Finnish group in arbitration proceedings against a construction company. The arbitral tribunal rejected the construction company’s claims in their entirety and ordered the construction company to reimburse our client for the costs of the arbitration proceedings in full. The dispute concerned the contract price under the construction contract, which was agreed to be determined on the basis of our client’s yield requirement and the rent under the lease agreement for the building in question. The parties disagreed on the indexation clause applicable to the rent adjustment and its impact on the contract price.
Case published 22.11.2024
We successfully represented a major Finnish construction company in a dispute and settlement negotiations concerning a large construction project. The dispute mainly concerned liabilities for additional and change works as well as project delays, and the value of the claims of the parties was approximately EUR 50 million.  If the case had not been settled, it would have been one of the largest construction disputes ever tried in the Finnish courts. The projected number of hearing days was unprecedentedly more than 300 days. To find an amicable solution to the extensive dispute, the parties engaged in settlement negotiations and court mediation. Eventually, the parties reached an amicable settlement to the full satisfaction of our client and thus the parties avoided the costs and risks of an extensive trial.
Case published 7.2.2024