24.9.2018

Renewable Energy Tenders are Won by Well-Planned Projects

Finland’s first tender process for accepting renewable electricity production into the new premium system will take place at the end of 2018. The purpose of the premium system is to promote renewable energy power plant investments in a technology-neutral fashion. Electricity produces can participate in the tender process with wind, biogas, wood fuel, solar or wave power investments. In addition to wind power, the subsidies paid in the premium system are expected to go to electricity produced from wood fuel in particular.

The upcoming tender process will accept a maximum yearly production amount of 1.4 TWh into the premium system from renewable power plants. The filing period for the Energy Authority’s tender process being organised this autumn is 15 November–31 December 2018. Arranging this kind of tender process requires that separate authorisation is included in the government budget. This being the case, the time of the next potential tender process has not yet been confirmed.

Premium and Annual Production Bids

The most cost-effective and competitive projects will win the tender process. Project developers have to submit binding bids for the subsidy level (euros/MWh) (premium) at which they are willing to produce a certain amount of energy (MWh) per year. Each winning project developer will receive a maximum subsidy of the amount of the premium in their bid for the energy they produce. The maximum premium allowed in the bids is 53.5 euros/MWh

The bid must also state the power plant intended to produce the electricity. It will be possible to supplement the information in the bid later on as the implementation of the project progresses by stating the aggregate nominal output or range of the power plant’s generators or solar panels. The final power plant must be notified to the Energy Authority within the limits of the stated range no later than two months after three years have passed from the decision accepting the power plant into the premium system being issued.

General Requirements

To participate in the tender process, renewable energy projects must be carefully planned and be far into development. In order for a power plant project to be accepted into the premium system, the project has to meet the requirements set in the Act on Electricity Produced from Renewable Energy Sources (1396/2010, as amended):

Electricity Producers Will Be Required to Post Security in Two Stages

In addition to being far into development, electricity producers will be required to post security for the fulfilment of their obligations both during the tender process and during the implementation phase.

First, electricity producers will be required to post a participation security for the Energy Authority when the producer files its bid. The amount of the participation security is the amount of yearly electricity production multiplied by 2 euros/MWh. The participation security must be valid until 30 June 2019. The participation security will be returned to the producers of losing bids when the results of the tender process are determined.

The electricity producers with winning bids will get their participation security back when they post a construction security for the Energy Authority, the amount of which is the amount of yearly electricity production multiplied by 16 euros/MWh. If the construction security is not posted within a month of the acceptance decision being given, the decision will lapse and the participation security will not be returned to the producer. The construction security must be valid for at least three years and six months.

Guarantees, guarantee insurance or pledged deposits issued by credit institutions or insurance companies or other professional financial institutions will be accepted as participation and construction security. The Energy Authority has published a template for the security to be posted.

After Acceptance

The electricity producer must at least partially connect its power plant to the power-distribution network in such a way that the plant produces electricity into the network within three years of being accepted into the premium system. The deadline is calculated from the date the acceptance decision was given. If the power plant is only partially connected to the power-distribution network within the three-year deadline, the construction security posted by the producer will be partially realised. If the power plant is not connected to the network even in part within the three-year deadline, the construction security will be realised in full.

Furthermore, if the power plant has not been fully connected to the power-distribution network in such a way that it fully produces electricity into the network within five years due to a reason attributable to the producer, the acceptance decision will lapse and the power plant project will be excluded from the premium system.

Falling below the amount of power generation stated in the bid will lead to sanctions. The electricity producer is obligated to pay underproduction compensation to the state if it does not produce the accepted amount of power. The power plant’s average output must be at least 75% of the yearly production during the first four-year ‘subsidy period’, and at least 80% during subsequent periods. The underproduction compensation is determined based on the premium in the bid and the amount of underproduction. However, the electricity producer will not be obligated to pay underproduction compensation if the shortfall is attributable to the system operator.

Electricity producers accepted into the premium system also have other obligations relating to, for example, the implementation of the power plant and reporting.

Latest references

We successfully represented a panel of reinsurance companies in an international ad hoc arbitration. The dispute arose out of a reinsurance treaty under the terms of which the reinsurers had reinsured a portfolio of risks underwritten by the cedent. The parties disagreed as to whether the reinsurance provided coverage for a certain loss that had occurred because of the market turmoil caused by the Covid-19 pandemic. The case involved highly complex legal and contractual questions requiring special expertise on reinsurance law and practice. The arbitral tribunal rejected the counterparty’s claims for reinsurance compensation against our clients in full. The amount in dispute was approximately EUR 34 million.
Case published 16.9.2025
We supported byFounders.vc as the Finnish counsel in their investment in DataCrunch Oy in a USD 64 million Series A funding round. DataCrunch provides scalable AI compute solutions from energy-efficient data centers in Iceland and Finland. byFounders.vc is the community-powered early-stage venture fund investing in globally ambitious teams connected to the Nordic and Baltic countries.
Case published 11.9.2025
We advised Springvest Oyj in organising a EUR 45 million Series A funding round for ReOrbit, a space technology company and a leading provider of software-first satellites. It’s the largest all-equity Series A round in Finland and one of the most significant deals overall in the European space and defence sector. The purpose of the funding round is to support ReOrbit’s growth. The round consisted of a private placement reserved for professional and institutional investors, which included, e.g. Icebreaker.vc, Expansion VC, 10xFounders, Inventure VC, Varma Mutual Pension Insurance Company, and Elo Mutual Pension Insurance Company, and an EUR 8 million public share offering, which was oversubscribed within 4.5 hours. Springvest is a Finland-based investment firm that connects unlisted growth companies with investors. ReOrbit builds sovereign satellites and connected systems for national security.
Case published 9.9.2025
Castrén & Snellman advised the lead investors Ten Eleven Ventures and Tesi in the EUR 275 million Series B financing round of IQM Quantum Computers, the global leader in building quantum computers. The round is largest Series B round ever in Finland and the second largest in the Nordics. In addition to the lead investors represented by C&S, the round was participated by several new and existing investors, including pension funds Elo Mutual Pension Insurance and Varma Mutual Pension Insurance, strategic investors Companies of Schwarz Group and Winbond Electronics Corporation, and sovereign wealth funds EIC and Bayern Kapital. Ten Eleven Ventures is the original cybersecurity-focused, global, and stage-agnostic investment firm. The firm identifies, invests in, and helps grow top cybersecurity companies addressing critical digital security needs, leveraging its team, network, and experience to build successful businesses. Since its founding, Ten Eleven Ventures has raised over USD 1 billion and made over 60 cybersecurity investments across various stages worldwide. Tesi (Suomen Teollisuussijoitus Oy / Finnish Industry Investment Ltd) is a state-owned investment company with an industrial policy mission focused on driving economic growth, renewal, and investments. Tesi invests on market terms both in venture capital and private equity funds, and directly in startups, scale-ups, and large industrial projects. IQM Quantum Computers, founded as a deep tech spin-off from Aalto University in 2019, specialises in developing quantum computers utilizing superconducting circuits. The company designs and produces quantum processors at its facility in Espoo, providing computing solutions and optimizations tailored to both research and industrial applications. In addition to its Finnish operations, IQM has expanded its presence to Germany, France, Italy, Japan, Poland, Spain, Singapore, South Korea, and the United States.
Case published 4.9.2025