Permitting Processes for Renewable Energy Plants Being Streamlined

Related services

On 4 January 2020, Parliament passed the Act on permit granting processes and certain other administrative procedures for renewable energy plants (1145/2020) (in Finnish laki uusiutuvan energian tuotantolaitosten lupamenettelyistä ja eräistä muista hallinnollisista menettelyistä) with the purpose of streamlining and speeding up the permitting processes and certain other administrative procedures for renewable energy plants. The act will enter into force on 30 June 2021.

The new act will enable developers of renewable energy plants to handle their project’s permitting and other administrative procedures listed in the act in a centralised manner through one electronic contact point. Furthermore, the act lays down firm time limits for the maximum duration of permitting processes and other administrative approval procedures for renewable energy plants (i.e. electricity production plants).

The act does not amend the contents of or requirements for the actual permit granting processes or other administrative procedures for renewable energy plants.

The act nationally implements the regulations concerning the organisation and duration of the permit granting process for renewable energy plants provided for in the EU directive on the promotion of the use of energy from renewable sources (EU) No 2018/2001 (RED II).

Electronic Service and Centralised Guidance for Renewable Energy Plants

In the future, the project developer of a renewable energy plant (the applicant) will not be forced to deal separately with many different authorities depending on what permit or approval they are applying for.

Going forward, the applicant can apply through a single electronic contact point for the permits and other administrative approvals listed in the act to build and repower the plant, to connect the plant to the grid and to operate it.

The electronic contact point is administered by one contact point authority, which is the Centre for Economic Development, Transport and the Environment for South Ostrobothnia (ELY Centre). However, permit matters are still resolved by the competent authority specified in the legislation applicable to the permit matter.

As the contact point authority, the ELY Centre for South Ostrobothnia is also obligated to advise applicants in procedural questions (e.g. questions relating to the initiation of a matter and the stage of a procedure) and to give applicants guidance relating to the handling of an administrative matter in cooperation with the competent authority through the electronic contact point.

The applicant can still deal directly with the competent permit authority instead of using the electronic contact point if they so wish.

Time Limits for Permitting and Approval Processes

The act lays down the maximum total duration for the permit processes and other administrative approval procedures for renewable energy plants listed in the act:

The time limits mentioned above only apply to power plants (i.e. plants producing electricity) and not, for instance, to heating plants or renewable fuel plants. However, the act does not define how much of the plant’s total energy production must be electricity production.

The applicable permit processes include, among other things, environmental permits, water permits, permits to deviate from the protection of certain aquatic habitat types and other habitat types, flight obstacle permits, permits to build high voltage cables, consent to build in the Finnish Exclusive Economic Zone, building, action and demolition permits and permits and deviations in areas requiring planning that are handled in connection with the building permit procedure.

The time limit begins to run when the applicant initiates the first applicable permitting process or approval procedure and ends when the last decision on an applicable permitting process or approval procedure has been delivered to the applicant. Thus, the time limit includes all stages of the process from initiation to the notification of the decision, including time limits for supplementing the application and statutory hearings. The applicant is not required to initiate all processes at the same time. However, the time limit does not include the appeal period or the time before the applicant has an applicable matter pending relating to the permitting process. The application of the time limits does not depend on whether the applicant uses the electronic contact point or deals directly with the competent authority.

In certain situations, the time limit set for the total duration can be extended by the same time that certain processes listed in the act require, including appealing a decision on an applicable permit or approval process. Furthermore, the contact point authority can grant a discretionary extension not exceeding one year to the time limit due to exceptional circumstances.

As the contact point authority, the ELY Centre for South Ostrobothnia is obligated to monitor the realisation of the time limits laid down in the act for the duration of permit processes. There are no sanctions for the authorities for exceeding the time limits, but the applicant can resort to general remedies, such as filing an administrative complaint or a complaint to the supreme guardians of the law. Whether or not the binding time limits will actually shorten the authorities’ processing times with respect to plants producing electricity from renewable sources remains to be seen once the act is implemented.

Latest references

We are assisting eQ Commercial Properties Fund in the sale of a fully let property to Logistea AB (publ), with an underlying property value of EUR 25 million. The property is transferred through the sale of the shares in the property-owning company Kiinteistö Oy Hämeenlinnan Länsiportintie 15. Logistea is a Swedish real estate company focusing on warehousing, logistic and light industrial properties, and its shares are listed on Nasdaq Stockholm. The property was built in 2012, and it is located in Hämeenlinna. The property has a total lettable area of approximately 21,700 square meters and the entire property is leased by Faerch Finland Oy, a fully owned subsidiary to Faerch A/S which is a leading provider of sustainable, circular food packaging solutions.
Case published 5.6.2025
We advised Gasum when it acquired 100% of the shares in NSR Biogas AB and the remaining 1/3 of the shares in Liquidgas Biofuels Genesis AB. Gasum has already been the majority owner of Liquidgas Biofuels Genesis AB since 2023 and is now acquiring full ownership. Gasum is a Nordic gas sector and energy market expert. Gasum offers cleaner energy and energy market expert services for industry and for combined heat and power production as well as cleaner fuel solutions for road and maritime transport. The company helps its customers to reduce their own carbon footprint as well as that of their customers.
Case published 5.6.2025
We acted as legal adviser to Efima Oyj in its acquisition of the entire share capital of Sparta Consulting Oy, a leading data management consulting firm. The acquisition strengthens Efima’s position as a strategic development partner for large and medium-sized enterprises and supports the company’s growth strategy and ability to meet the growing demand for intelligent, data-driven business solutions. Founded in 2012, Sparta Consulting specialises in comprehensive information management, and its clients are primarily large Finnish companies in the banking and insurance, energy, and telecommunications sectors. Efima Oyj is a Finnish digital company that promotes the growth of large and medium-sized enterprises by streamlining and automating business processes and creating competitive advantage through innovative use of artificial intelligence and data. The company has over 250 experts in Helsinki and Tampere.
Case published 3.6.2025
We advised Pihlajalinna Plc on an arrangement whereby Pihlajalinna Terveys Oy and Ikipihlaja Setälänpiha Oy sold their special housing services business to Esperi Care Oy.  The transaction involved three Pihlajalinna Uniikki units in Hämeenlinna, Lohja and Riihimäki as well as Ikipihlaja Oiva in Raisio. As a result of the arrangement, more than 100 employees transferred to Esperi. Pihlajalinna is one of Finland’s leading private providers of social and healthcare services, offering a wide range of services to both private and public sector clients. Pihlajalinna has more than 160 locations across Finland.
Case published 2.6.2025