26.10.2016

Asphalt Cartel Damages Case: Helsinki Court Of Appeal Dismissed All Claims Against Our Client

Helsinki Court of Appeal gave its judgments in the so-called asphalt cartel follow-on damages cases on 20 October 2016. On 29 September 2009, the Finnish Supreme Administrative Court found that several asphalt companies had participated in a cartel. Now, the Helsinki Court of Appeal ordered the asphalt companies to compensate a total of 24 million euros to the State of Finland and 39 local municipalities, in effect dismissing the majority of the damages claims, which amounted to 120 million in total.

The Court of Appeal dismissed some of the claims as time-barred, while others were dismissed due to a lack of evidence of the infringement or of damage or due to an inadequately proven causal connection.

In addition, the Court of Appeal dismissed all claims against respondents that had not participated in the concerted practice, but had later acquired the business and shares of the companies participating in the competition restriction. Unlike the Helsinki District Court, the Court of Appeal concluded that the awareness of the representatives of the Finnish State of or their participation in the competition restriction did not exclude the Finnish State’s right to compensation. Thus, the Court of Appeal accepted some of the State’s claims.

Principle of Economic Succession Not Applicable

This case marked the first time that the Court of Appeal ruled on the applicability of the principle of economic succession as legal grounds for liability for damages. Economic succession is a principle developed in the legal praxis of the CJEU in relation to the imposition of fines. According to the principle, the economic operation attributable to the infringement shall be liable for it.

In practice the principle means that the liability for fines can be imposed on a third party that did not itself participate in the restriction of competition. Fines can be imposed, for example, on the purchaser of a business for actions taken by that business in the period preceding the purchase.

According to the Court of Appeal, there are no grounds based on EU law for applying the principle of economic succession to liability for damages. Instead, liability must be based on Finnish law. There is no general rule in Finnish tort law according to which economic succession alone would allow liability for damages to be transferred onto a third party outside of the sphere of responsibility of the parties in breach.

Economic succession was also left out of the Act on Competition Damages, which enters into force on 26 December 2016.

Limitation Period Based on Injured Party’s Awareness Started When Fines Were Proposed

The Court of Appeal also found that the limitation period based on the claimants’ awareness started when the Finnish Competition Authority made a proposal for fines to the Market Court. The Court of Appeal reached this conclusion based on the evidence, and it is in line with the recent judgment of the Finnish Supreme Court in the raw wood cartel damages case.

In addition, the 10-year limitation period that is not dependent on awareness started from the date of the payment of the contract price. The Supreme Court’s evaluation of awareness will also remain valid when assessing the limitation period under the forthcoming Act on Competition Damages.

Existence of an Infringement, Causal Connection and Alleged Damages

The Court of Appeal stated that it was not bound by the circumstances underlying the judgment of the Supreme Administrative Court in the penalty payment matter. This means that the judgment does not have res judicata nor any special evidentiary effect in subsequent damages proceedings.

According to the Court of Appeal, the assessment of evidence cannot be based on the prior judgment even when the presented evidence concerning the existence and scope of the restriction of competition is the same. Even though a wider arrangement existed in the background, the Court of Appeal emphasised that the effect of the market partitioning and related bidding co-operation on the price level of the relevant contract is a matter that must be assessed separately for each individual tender procedure.

The Court of Appeal assessed the content and the scope of the infringement in a manner that partially diverged from the Supreme Administrative Court regarding, among other things, the duration and geographic scope of the infringement. According to the aforementioned Act on Competition Damages, the judgment of the administrative court should be taken as a starting point in a damages case. The act also includes a damage presumption regarding cartels, which the defendant can reverse, for example, with evidence regarding the lack of a causal connection that the Court of Appeal assesses in connection with each separate contract.

In its decisions, the Court of Appeal also assessed several other significant questions that will remain relevant in the future. These include, among other things, joint and several liability, interest and the quantum of damages. The judgments of the Court of Appeal are not yet final. 

Latest references

We advised Hopeasalmen Telakka Oy, part of Marina Group, on the acquisitions of Iisiveneily and Porvoon Venekorjaamo. The transactions form part of Marina Group’s expansion into the Finnish marina and boatyard sector, strengthening its position under the Quattro Marine brand. Following the acquisitions, Quattro Marine’s Finnish operations comprise Hopeasalmen Telakka, which operates boatyard facilities in Helsinki’s Mustikkamaa and in Tolkkinen, Porvoo, together with Iisiveneily and Porvoon Venekorjaamo. Marina Group is a Norwegian marina and boatyard consortium owned by the private equity sponsor Norvestor. It has grown rapidly through acquisitions to become the Nordic region’s largest boating services provider, having acquired 24 marinas and boatyards across Norway, Sweden and Finland within roughly a year.
Case published 24.8.2026
We advised Neste as it signed a EUR 250 million 10-year loan with NIB. The loan will finance Neste’s investments related to research and development (R&D) in processing lower-quality feedstocks into high-quality renewable products; as well as the liquefied waste plastics (LWP) investment at Neste’s refinery in Porvoo, Finland. The R&D activities supported by the loan focus on the development of renewable solutions. These include, for example, expanding feedstock capabilities and technologies that enable the processing of new and lower-quality waste and residues into high-quality renewable end products. Part of the financing supports Neste’s liquefied waste plastics investment in Porvoo, related to upgrading low-quality plastic waste into high-quality feedstock at an industrial scale. The investment contributes to advancing circular economy solutions by enabling the use of hard-to-recycle plastic waste as a replacement for virgin fossil raw materials. The unit has an annual capacity to process up to 150,000 tonnes of liquefied waste plastic. Production ramp-up commenced in 2026.
Case published 19.8.2026
We advised Aspo Plc, ESL Shipping Ltd and AtoBatC Shipping AB in relation to finance matters in connection with the demerger of Aspo, by which all the shares in ESL Shipping Ltd held by Aspo, together with the related assets and liabilities, will be transferred to a new independent company to be named ESL Shipping Group Plc. Aspo intends to apply for the shares of ESL Shipping Group to be admitted to trading on the regulated market of Nasdaq Helsinki. It is further intended that Aspo be renamed Telko Group Plc. 
Case published 19.8.2026
We acted as Finnish law legal adviser to the lenders and the export credit agencies in connection with the EUR 514.4 million green project financing for the development and construction of Easpring Finland New Materials Oy’s cathode active material (CAM) manufacturing plant in Kotka, Finland. The borrower, Easpring Finland New Materials Oy, is a joint venture owned by Beijing Easpring Material Technology, Finnish Minerals Group and LG Energy Solution. The financing was provided by six international commercial banks, with Société Générale acting as financial adviser and mandated lead arranger together with Natixis as co-mandated lead arranger, and DNB, ICBC, ING and Standard Chartered participating as lenders, with support from the export credit agencies Finnvera and Sinosure. The project represents a significant milestone for Finland and the European battery value chain by strengthening Europe’s domestic supply of cathode active materials, a key component in lithium-ion batteries for electric vehicles and energy storage applications. Once the first phase of the project is operational, the Kotka facility is expected to produce approximately 60,000 tonnes of cathode active material annually, making it one of the largest CAM production plants in Europe and supplying leading battery manufacturers across Europe. 
Case published 21.7.2026