28.5.2015

New Government Programme: The End of an Era for Wind Power in Finland?

On Wednesday 27 May 2015, Finland’s next government reached an agreement on its new government programme. One of the planned changes concerns Finland’s feed-in-tariff system, which is now worrying Finland’s wind power market–and with good reason.

Based on the current legislation, the Finnish feed-in-tariff is available for new wind farms to be built in Finland up to an aggregate power of 2,500 MVA. Approximately 72% of this capacity has already been reserved at this point.

The new proposal is to cut the quota from 2,500 MVA to 2,000 MVA. This means that there may be room for an additional 312 MVA. This is still unclear.

Is this now the end for new wind power developments? No, but we need clear guidelines and legislation on what will happen after the current subsidy programme.

In practice, this change will have no impact on the wind power projects to be installed during the next two to three years as they have already been admitted to the feed-in-tariff system. In fact, it means the ramping up of wind power faster than anyone expected. This is good news.

The bad news is that several wind power developers may face insolvency due to a lack of interest by international investors if there is no clear future for the next subsidy programme. Parliament should now focus on safeguarding the continuous construction of wind power beyond the current feed-in tariff programme.

I am positive that there are investors willing to invest in Finland even after the feed-in-tariff is no longer available. However, this will require clear and transparent discussion of the next subsidy arrangement. Otherwise, the whole wind farm sector will freeze after 2017.  This would mean that the whole development base of wind power, approximately 11,000 MW, could be wasted.

Latest references

Castrén & Snellman advised Nscale, a European AI infrastructure company, in connection with its planned data centre project in Harjavalta, Finland. The facility will be located in the Sievari industrial area. Castrén & Snellman’s advisory role encompassed the negotiation and execution of a site securing and development agreement (SSDA) with Fortum, as well as the preliminary land sale process for the Sievari site with the Town of Harjavalta. Under the SSDA, Fortum supports the advancement of Nscale’s project development, including grid connection design and permitting.
Case published 15.4.2026
We advised Gasum Oy in its acquisition of 100% of the shares in Hærup Biogas ApS, which owns and operates a biogas plant in the northern part of mainland Denmark. This acquisition marks Gasum’s first biogas plant in Denmark, expanding its biogas production portfolio. Gasum’s strategic goal is to bring seven terawatt hours of renewable gas to the Nordic market yearly by 2027. The acquisition is one step towards achieving the strategic goal. Gasum is a Nordic gas sector and energy market expert. Gasum offers cleaner energy and energy market expert services for industry and for combined heat and power production as well as cleaner fuel solutions for road and maritime transport. The company helps its customers to reduce their own carbon footprint as well as that of their customers. 
Case published 3.12.2024
We assisted DNA with their 10-year power purchase agreement (PPA) with Statkraft. The PPA enables DNA to buy 85 gigawatt-hours of clean energy per year from the new Palokangas wind farm, owned by investment firm Exilion Tuuli. The project, which will come online in late 2024, will generate 80% of DNA’s power needs. The Palokangas wind farm will be located in the Ostrobothnia region and equipped with 12 turbines.
Case published 15.8.2023
We are advising Oomi Oy in questions relating to electricity market legislation, consumer protection and marketing law. Oomi is one of the largest electricity sales companies in Finland. The company sells electricity contracts, solar power systems and electric car charging solutions to consumers and businesses.
Case published 19.6.2023