Finland proposes a new data centre register – draft legislation open for comments

The Finnish Ministry of Economic Affairs and Employment has published a draft government proposal to establish a national data centre register and to introduce reporting obligations for data centre operators.

The new register would improve the shared situational picture of data centre investments and operations, which was one of the objectives identified in Finland’s National Roadmap for Data Centres last year. The roadmap also formed the basis for preparing a dedicated tax support scheme for data centres; however, at its autumn 2026 budget session, the Government of Petteri Orpo stated that it would not proceed with the scheme.

Who would be required to register?

The obligation to register would apply to planned data centres with an expected installed IT power demand of at least 0.5 MW, including technically and functionally integrated buildings and known phased expansions. The obligation would fall primarily on the data centre operator or, if no operator has been appointed, the direct owner of the data centre or the property, building or other asset comprising it.

When would the notification need to be made?

For new projects, the notification would be required after the investment decision but before the start of the construction works. Data centres already under construction or in operation when the legislation enters into force – currently envisaged for the beginning of next year – would need to register by 30 June 2027.

What information would need to be reported?

The notification would require the following information on the data centre, its operations, energy use and infrastructure:

  • the data centre’s name and location;
  • information on the direct owner, operator and entities exercising control over the data centre;
  • the intended use of the data centre;
  • planned implementation schedule for the data centre or its expansions;
  • estimates of annual electricity consumption and electricity demand for the following five years, as well as future electricity grid and infrastructure needs;
  • estimated employment impacts during construction and operation;
  • installed IT power demand and maximum electricity connection capacity;
  • energy efficiency (PUE);
  • the size of the property and the floor areas of the data centre and server rooms; and
  • information on backup power, on-site energy production, energy storage, demand response and plans for the utilisation of waste heat.

Duty to provide updates

Material changes concerning ownership, control, operation, suspension or termination of the project, or the scale or nature of the data centre, would generally need to be reported within 30 days.

Supervision and enforcement

The National Emergency Supply Agency (Huoltovarmuuskeskus) would maintain the register and supervise compliance. It could impose a conditional fine for failure to submit a required notification or for submitting a materially deficient one.

Exchange of information between authorities

The Agency could obtain confidential information from certain authorities and would be required to share certain information with relevant governmental, municipal and wellbeing services county authorities in order to support the national situational picture of data centres.

Importantly, registration would not constitute an operating permit and could not, in itself, be used to approve or prevent a data centre project or to impose conditions on an investment.

Next steps

The proposed legislation is intended to enter into force on 1 January 2027. The draft proposal is open for comments until 2 October 2026, giving data centre operators an opportunity to consider the scope and detail of the proposed reporting requirements and to raise any relevant concerns.

With extensive experience in advising data centres, our team would be happy to discuss the proposal and the consultation process.

Latest references

We acted as legal adviser to Banyan Software on its acquisition of Carus Ferry, a Finland-based provider of reservation, check-in and port operations software for ferry and passenger shipping operators. The acquisition further strengthens Banyan Software’s presence in the Nordic region while providing Carus with a long-term partner to support its continued growth and development. Carus was founded in 1998 and is headquartered in Mariehamn on the Åland Islands, Finland. The company develops mission-critical software for ferry, cruise and passenger shipping operators, covering the full passenger journey from booking and ticketing to capacity management, check-in and boarding. Carus also provides port automation, onboard sales systems and business information tools. The company serves approximately 30 operators across four continents and is the largest vendor by customer count in ferry reservation and departure control. Banyan Software is an acquirer and long-term operator of mission-critical software businesses serving specialised industries. Founded in 2016, Banyan follows a buy-and-hold-for-life approach and supports the long-term growth and development of its portfolio companies. Banyan operates more than 130 portfolio companies across North and South America, the United Kingdom, Europe and APAC. Following the acquisition of Carus, Banyan operates three businesses in the Nordic region.
Case published 20.10.2026
We advised Move Energy as an investor in connection with the combination of 3North Partners Plc and Steady Energy Oy and the related private placement and initial public offering of the combined company on Nasdaq First North Growth Market Finland. In connection with the transaction, 3North Partners received approximately EUR 69.8 million in investor commitments from a group of institutional and other investors, including Move Energy, to fund the combined company. Steady Energy is a Finnish nuclear technology company developing a new generation of small modular reactors (SMRs) particularly suited for district heating. Its LDR-50 reactor is designed to provide cities and utilities with a scalable and low-carbon alternative to combustion-based heat production.
Case published 19.10.2026
We advised Efima Oyj on the sale of its AI business to Better Care Technologies Oy. The transaction included Efima’s Moiva AI platform developed for the care sector, the related technology and brand, customer contracts, and the experts working in the business. Efima is a Finnish digital company that supports the sustainable growth of large and mid-sized companies by streamlining their business processes and by creating competitive advantage through the innovative use of artificial intelligence and data. The company has nearly 200 experts based in Helsinki and Tampere. 
Case published 21.9.2026
We advised Neoen Renewables Finland Oy, part of the French Neoen Group, in its sale of a data centre project to a consortium consisting of international data centre developers and operators. This marked Neoen’s first data centre development project in Finland. Founded in 2008, Neoen is one of the world’s leading independent renewable energy producers. The company operates in 15 countries. It develops, finances, builds, owns, and operates solar power plants, wind farms, and battery storage systems. Neoen Group is owned by global alternative asset manager Brookfield Corporation.
Case published 17.9.2026