Finland proposes a new data centre register – draft legislation open for comments

The Finnish Ministry of Economic Affairs and Employment has published a draft government proposal to establish a national data centre register and to introduce reporting obligations for data centre operators.

The new register would improve the shared situational picture of data centre investments and operations, which was one of the objectives identified in Finland’s National Roadmap for Data Centres last year. The roadmap also formed the basis for preparing a dedicated tax support scheme for data centres; however, at its autumn 2026 budget session, the Government of Petteri Orpo stated that it would not proceed with the scheme.

Who would be required to register?

The obligation to register would apply to planned data centres with an expected installed IT power demand of at least 0.5 MW, including technically and functionally integrated buildings and known phased expansions. The obligation would fall primarily on the data centre operator or, if no operator has been appointed, the direct owner of the data centre or the property, building or other asset comprising it.

When would the notification need to be made?

For new projects, the notification would be required after the investment decision but before the start of the construction works. Data centres already under construction or in operation when the legislation enters into force – currently envisaged for the beginning of next year – would need to register by 30 June 2027.

What information would need to be reported?

The notification would require the following information on the data centre, its operations, energy use and infrastructure:

  • the data centre’s name and location;
  • information on the direct owner, operator and entities exercising control over the data centre;
  • the intended use of the data centre;
  • planned implementation schedule for the data centre or its expansions;
  • estimates of annual electricity consumption and electricity demand for the following five years, as well as future electricity grid and infrastructure needs;
  • estimated employment impacts during construction and operation;
  • installed IT power demand and maximum electricity connection capacity;
  • energy efficiency (PUE);
  • the size of the property and the floor areas of the data centre and server rooms; and
  • information on backup power, on-site energy production, energy storage, demand response and plans for the utilisation of waste heat.

Duty to provide updates

Material changes concerning ownership, control, operation, suspension or termination of the project, or the scale or nature of the data centre, would generally need to be reported within 30 days.

Supervision and enforcement

The National Emergency Supply Agency (Huoltovarmuuskeskus) would maintain the register and supervise compliance. It could impose a conditional fine for failure to submit a required notification or for submitting a materially deficient one.

Exchange of information between authorities

The Agency could obtain confidential information from certain authorities and would be required to share certain information with relevant governmental, municipal and wellbeing services county authorities in order to support the national situational picture of data centres.

Importantly, registration would not constitute an operating permit and could not, in itself, be used to approve or prevent a data centre project or to impose conditions on an investment.

Next steps

The proposed legislation is intended to enter into force on 1 January 2027. The draft proposal is open for comments until 2 October 2026, giving data centre operators an opportunity to consider the scope and detail of the proposed reporting requirements and to raise any relevant concerns.

With extensive experience in advising data centres, our team would be happy to discuss the proposal and the consultation process.

Latest references

We advised Nala Renewables on the Finnish law aspects of the development, acquisition and financing of its battery energy storage system (BESS) project in Vuolijoki, Finland. The project comprises a 125 MW / 250 MWh battery energy storage system. Our advice extended beyond financing to the transaction’s legal due diligence and the acquisition of the project company. We also advised on key project contracts and financing documentation for the project finance facilities provided by Coöperatieve Rabobank U.A. The project is part of Nala Renewables’ growing portfolio of battery storage assets in Finland and the wider Nordic region, supporting the integration of renewable energy and contributing to the flexibility and stability of the Finnish electricity grid.
Case published 3.11.2026
We advised Foundation Clinic in connection with its funding round backed by a group of prominent Finnish technology entrepreneurs and investors, including founders behind Supercell and Wolt. Foundation Clinic is a Finnish healthcare company developing a new approach to private healthcare focused on preventive, data-driven and continuous care. The company aims to combine comprehensive health data with ongoing medical care to identify and address health risks at an early stage.
Case published 29.10.2026
We advised Delta Capacity AG in a project financing of two battery energy storage systems (BESS). The financed projects are among the largest BESS developments in Finland to enter construction with 250 MW / 600 MWh combined capacity. The financing was provided by Société Générale with support from Finnvera. Construction of both projects, located in Lapinlahti and Teuva, has already begun and the commercial operations are targeted to commence in late 2027 with partial tolling agreements already in place for both assets. The project in Lapinlahti is executed in partnership with Covenergo, while the project in Teuva is executed in partnership with Strioga Family Foundation. Delta Capacity is a Swiss developer of utility-scale battery storage systems. The projects strengthen Delta Capacity’s growing Nordic portfolio and support the flexibility of Finland’s electricity system by adding energy storage capacity, enabling production optimization as well as participation in electricity markets and reserve services.
Case published 28.10.2026
We acted as legal adviser to Martela Corporation in its directed share issue, through which Martela raised gross proceeds of approximately EUR 7.2 million to strengthen the company’s financial position and liquidity and to create headroom for continuing the necessary development and efficiency measures. In connection with the directed share issue, Martela’s unlisted series K shares, which carried greater voting rights, were combined with its listed series A shares. Following the combination, the company has only one share series, which is traded on the regulated market maintained by Nasdaq Helsinki Ltd, with each share carrying one vote and otherwise identical rights. Martela is a Nordic leader specialising in user-centric working and learning environments. With over 80 years of experience, Martela creates the best places to work and offers its customers the Martela Lifecycle solutions which combine furniture and related services into a seamless whole.
Case published 27.10.2026