14.4.2016

Concurrent Delays in International Construction Projects – a Finnish Law Point of View

My previous post on legal transplants covered endeavours clauses. In this article, I am addressing concurrent delays, which is another interesting topic from the perspective of international construction projects.

Concurrent Delay – The Phenomenon

Delays in general are a tricky business. As opposed to other types of contractual changes, such as variations, delays always imply negative consequences. These consequences are imposed on either the employer or the contractor of the project, depending on which is responsible for causing the delay. It is safe to say that neither party welcomes these consequences with open arms, but will rather try to avoid them at all cost. This being the case, delays usually carry the risk of conflict with them.

The risk of conflict tends to increase in the event of concurrent delays. A concurrent delay means a delay that has been caused by two or more events or circumstances at the same time. Even without one of these events, the delay would still have materialised. The problem with concurrent delay arises if both the employer and the contractor are each (at least partially) responsible for one of the events causing delay. 

An example of this would be a scenario where (1) the employer delays the review process of critical design documents (or delivery process of the same, depending on the type of project) and, meanwhile, (2) the contractor performs repairs on deficiently performed works, whilst (3) both of these actions affect the critical path of the project and delay its completion, events or circumstances at the same time. Even without one of these events, the delay would still have materialised. The problem with concurrent delay arises if both the employer and the contractor are each (at least partially) responsible for one of the events causing delay.

Does the contractor get an extension of time for the concurrent part of the delay despite the fact that, even without the employer’s delay, the project would have suffered an equal delay that the contractor is responsible for?

Concurrent Delays under English and Finnish Law

Unless the construction contract specifically addresses concurrent delays, the issue is subject to contractual interpretation. Under common law, there are at least two alternative approaches for handling concurrency (see link below): the ‘Malmaison Approach’ leans towards the contractor being granted an extension of time, whereas the  ‘Apportionment Approach’ implies that the responsibility for the delay could be apportioned between the two causes.

English courts have generally adopted the Malmaison Approach, and so under English law, unless otherwise agreed in the contract, the contractor would be granted an extension of time despite concurrency.

Under Finnish law, ultimately, the effect of concurrency will depend on the contract. The problem is that the wording can be very ambiguous as to concurrency. If the contract states that the Contractor shall be entitled to an extension of time if and to the extent that completion of the works is or will be delayed by acts of the Employer, the relevant question is has the completion in fact been delayed by the acts of the Employer considering that the same delay would have materialised independent of the Employer’s delay.

Practical Considerations

It is worth noting that ‘real’ concurrent delays are, in fact, quite rare. Sometimes, events only seem concurrent, because the programme (detailed schedule of the works) is not sufficient for verifying the actual critical path and the impact of each delay event on said critical path. This is important to keep in mind, since after all, in most large scale projects, it is not the delay as such that entitles the contractor to an extension of time; only delays to the completion of the project are relevant in this context.

In these circumstances, the question of concurrency could be avoided by both parties paying sufficient attention to drafting the programme initially and then keeping it up to date during the project execution. It may show that only one of the delays affected completion.

Concluding Remarks

Since delays in general tend to be a rather volatile topic, there is really no magic wording which would eliminate all risk of disputes relating to delays in a construction project. A good starting point, however, is to specify in the contract – and, importantly, to do so unambiguously – how concurrent delays are to be resolved, along with drafting a sufficiently detailed programme and keeping it mutually up to date at all times.

The programme should show the current critical path at any given time, all dependencies between the various phases of execution (also for those phases that are not on the critical path at that particular time), and the float included in the programme. This way, upon each delay causing event, the programme can be updated without unnecessary argumentation as to, for instance, the alternative chain of dependencies that form the new critical path as a result of the delay.

For common law discussion, see e.g.:
http://www.elexica.com/en/legal-topics/construction/16-concurrent-delays-in-construction-projects

 

Latest references

We are acting as the lead counsel to Fortum in a cross-border transaction in which Fortum is selling its recycling and waste business. The business is sold to thematic impact investing firm Summa Equity through its portfolio company NG Group. The debt-free purchase price is approximately EUR 800 million. The transaction is subject to authority approval and customary closing conditions. Fortum’s recycling and waste business to be sold comprises municipal and industrial waste management and end-to-end plastics, metals, ash, slag and hazardous waste treatment and recycling services. These businesses are located in Finland, Sweden, Denmark and Norway and currently employ approximately 900 employees.
Case published 18.7.2024
We advised WasaGroup Ltd in a green transition project where WasaGroup will plan Hitachi Energy’s new production and technology campus in Mustasaari. WasaGroup will be responsible for planning, permitting, managing and conducting the entire project as well as for the tender processes. We advised WasaGroup in drafting and commenting the project management and financing agreements for the project. The Mustasaari campus will be approximately 30,000 square meters in size. The investment by Hitachi Energy will double the capacity for transformer production in Finland, and the product range will expand to include even larger transformers. The objective of the investment is to meet the demand for transformers and other modern technology that is increasing in Finland and internationally due to the green energy transition. The first phase of the project involved an agreement for a development project to prepare the building permit and reach sufficient planning readiness for the implementation of the project. The aim is to have the production and technology campus in use by 2027.
Case published 30.5.2024
We successfully represented a major Finnish construction company in a dispute and settlement negotiations concerning a large construction project. The dispute mainly concerned liabilities for additional and change works as well as project delays, and the value of the claims of the parties was approximately EUR 50 million.  If the case had not been settled, it would have been one of the largest construction disputes ever tried in the Finnish courts. The projected number of hearing days was unprecedentedly more than 300 days. To find an amicable solution to the extensive dispute, the parties engaged in settlement negotiations and court mediation. Eventually, the parties reached an amicable settlement to the full satisfaction of our client and thus the parties avoided the costs and risks of an extensive trial.
Case published 7.2.2024
Valio is a food company with the courage to change with the times. Valio’s road to growth and towards the innovative transformation of the food industry is supported by its long-standing business law partner, Castrén & Snellman. Juha Hölttä became Valio’s General Counsel at a time when the company kicked its new strategy into a higher gear. ‘In the past two years we have made several significant market initiatives and expanded our business from food production to other areas of the value chain. By acquiring Heinon Tukku, we now provide a new kind of added value to restaurants and professional kitchens through our Valio Aimo ® wholesale business. And our joint venture with St1, Suomen Lantakaasu Oy, will enable us to reach our goal of turning manure into biogas for heavy transportation,’ Hölttä describes some of the milestones of the new strategy. In addition to expanding into new business areas, Valio continues to build a more sustainable dairy business alongside seeking international growth from plant-based products. Valio has invested in the international growth of its Oddlygood ® brand through incorporation and gained additional product development expertise through the acquisition of Gold&Green. Carbon footprint of milk reduced by new business operations Dairy products are at the core of Valio’s business, and the company develops this strong foundation not only through product innovation but also at the beginning of the food chain. ‘Who could have foreseen that dairy farm manure could become one way of tackling climate challenges? Our planned biogas plants will use manure and agricultural by-products to produce renewable liquefied biogas for use as transportation fuel,’ says Hölttä. ‘Valio is aiming for a carbon-neutral milk chain by 2035. We are making major reforms in our operations in order to make this happen.’ The sustainability programme for Valio’s 3,700 dairy farms has been expanded, and it now includes the preventive and systematic healthcare of cows as well as actions related to grazing, the climate and biodiversity. ‘Appreciation for locally produced food is on the rise, which means that sustainability questions are local as well. This is a good trend, as it makes it easier for us to make a difference.’ ‘Strategic help even in difficult circumstances’ The service-mindedness of lawyers is key in implementing a growth strategy. Castrén & Snellman Attorneys is a long-standing partner of Valio, and the relationship between the two is tight. ‘At Valio, we are always exploring new business opportunities, and us lawyers are tasked with assessing these opportunities. My philosophy as the General Counsel is that my door is always open. Together we can evaluate how to solve and implement new initiatives. In this job, you must be curious, broad-minded and business-oriented,’ summarises Hölttä. Hölttä’s legal team of five people is supported by experts from Castrén & Snellman. The key to successful partnership is that both parties are familiar with each other’s business operations and ways of working. ‘Castrén & Snellman knows us well, and they maintain an up-to-date overview of our situation, which I highly appreciate. It means that we are able to tackle tricky situations together quickly even in difficult circumstances.’ A joint fast reaction was needed, for example, when Valio exited the Russian market after the country launched its war of aggression on Ukraine. ‘The responsible thing was to leave quickly but in a controlled manner and by repatriating our investment as opposed to leaving an operational food production facility in the hands of a country that was waging war.’ A shared vision of sustainability Valio – Together we make life better A Finnish food company Approx. 4,600 employees Owned by 13 Finnish dairy cooperatives Finland’s most sustainable brand in the Sustainable Brand Index study Read more about sustainability at Valio Castrén & Snellman – Building sustainable success stories Forerunner of demanding legal services 300 employees Owned by its partners ‘We help our clients build sustainable success stories and achieve their sustainability goals.’ Read more about sustainability at Castrén & Snellman Shared success stories of Valio and C&S Global Brand Portfolio Management and IP Enforcement Purchase of Gold&Green’s Brand, IPR and R&D Function Joint Venture for Biogas Production with St1 Sale of Russian Operations Acquisition of Heinon Tukku Significant Growth Funding Round Competition Damages Case Defending Against Environmental Permit Challenge at the Appellate Level
Case published 4.5.2023