19.6.2023

Latest news in climate law: the appeal concerning the sufficiency of the state’s climate actions ruled inadmissible by the SAC

Background

Finland’s new Climate Act entered into force in July 2022. Amendments to the Act were approved in December 2022, and on 1 January 2023 the Climate Act was amended with provisions that concern appealing decisions made thereunder.

On 28 November 2022, before the amendments entered into force, the Finnish Association for Nature Conservation and Greenpeace Norden filed an appeal to the Supreme Administrative Court, requesting that the Finnish Government’s decision on the Annual Climate Report 2022 be revoked and sent back to preparation. This was the first time the sufficiency of the state’s climate actions was challenged in court in Finland. According to the NGOs, the Government had failed in its duty to take the necessary additional actions in terms of carbon sinks to ensure the realisation of the targets set out in the Climate Act.

Supreme Administrative Court ruled the appeal inadmissible

Under its decision of 7 June 2023, the Supreme Administrative Court (SAC) dismissed the NGOs’ appeal.

The SAC examined the admissibility of the appeal very broadly, referring for example to the Finnish constitution. While the SAC ended up ruling the appeal inadmissible, it stated, among other things, that assessing the legality of the Government’s decision-making as intended by the appellants could be examined by the court in such a case that failure to make a decision would lead to an outcome contrary to the Climate Act or that the Government’s actual actions would show that it has no intention of making appropriate decisions in order to achieve the goals and obligations required by the Climate Act in a sufficiently short time frame.

The SAC further stated that the appealability of the Annual Climate Report should not be assessed differently based on the regulation on appeals under the amended Climate Act.

Case law regarding climate actions likely to be specified in future

It is noteworthy that pursuant to the SAC’s decision, the passiveness of the Government could be examined by the court in the abovementioned situation. Furthermore, the decision of the SAC was reached only after a vote. The minority of the formation of the court found the Government decision to be admissible for appeal. Therefore, it is to be expected that the sufficiency of the Government’s climate actions will be challenged in Finnish courts again.

See also:

Latest news in climate law: Climate Act amended and Finland’s first climate litigation case filed

New Climate Change Act aims at carbon neutrality

Latest references

We advised Nala Renewables on the Finnish law aspects of the development, acquisition and financing of its battery energy storage system (BESS) project in Vuolijoki, Finland. The project comprises a 125 MW / 250 MWh battery energy storage system. Our advice extended beyond financing to the transaction’s legal due diligence and the acquisition of the project company. We also advised on key project contracts and financing documentation for the project finance facilities provided by Coöperatieve Rabobank U.A. The project is part of Nala Renewables’ growing portfolio of battery storage assets in Finland and the wider Nordic region, supporting the integration of renewable energy and contributing to the flexibility and stability of the Finnish electricity grid.
Case published 3.11.2026
We advised Delta Capacity AG in a project financing of two battery energy storage systems (BESS). The financed projects are among the largest BESS developments in Finland to enter construction with 250 MW / 600 MWh combined capacity. The financing was provided by Société Générale with support from Finnvera. Construction of both projects, located in Lapinlahti and Teuva, has already begun and the commercial operations are targeted to commence in late 2027 with partial tolling agreements already in place for both assets. The project in Lapinlahti is executed in partnership with Covenergo, while the project in Teuva is executed in partnership with Strioga Family Foundation. Delta Capacity is a Swiss developer of utility-scale battery storage systems. The projects strengthen Delta Capacity’s growing Nordic portfolio and support the flexibility of Finland’s electricity system by adding energy storage capacity, enabling production optimization as well as participation in electricity markets and reserve services.
Case published 28.10.2026
We advised Neoen Renewables Finland Oy, part of the French Neoen Group, in its sale of a data centre project to a consortium consisting of international data centre developers and operators. This marked Neoen’s first data centre development project in Finland. Founded in 2008, Neoen is one of the world’s leading independent renewable energy producers. The company operates in 15 countries. It develops, finances, builds, owns, and operates solar power plants, wind farms, and battery storage systems. Neoen Group is owned by global alternative asset manager Brookfield Corporation.
Case published 17.9.2026
We acted as Finnish law legal adviser to the lenders and the export credit agencies in connection with the EUR 514.4 million green project financing for the development and construction of Easpring Finland New Materials Oy’s cathode active material (CAM) manufacturing plant in Kotka, Finland. The borrower, Easpring Finland New Materials Oy, is a joint venture owned by Beijing Easpring Material Technology, Finnish Minerals Group and LG Energy Solution. The financing was provided by six international commercial banks, with Société Générale acting as financial adviser and mandated lead arranger together with Natixis as co-mandated lead arranger, and DNB, ICBC, ING and Standard Chartered participating as lenders, with support from the export credit agencies Finnvera and Sinosure. The project represents a significant milestone for Finland and the European battery value chain by strengthening Europe’s domestic supply of cathode active materials, a key component in lithium-ion batteries for electric vehicles and energy storage applications. Once the first phase of the project is operational, the Kotka facility is expected to produce approximately 60,000 tonnes of cathode active material annually, making it one of the largest CAM production plants in Europe and supplying leading battery manufacturers across Europe. 
Case published 21.7.2026