Additional Clarity Expected for the Mining Sector as the Renewal of the Mining Act Proceeds

The Ministry of Employment and the Economy published earlier this August, a preliminary proposal for amendments to the Finnish Mining Act that are in line with the Government Programme of Prime Minister Marin.

In general, the proposal reflects the need for higher environmental and social standards, and reinforces the rights of the municipalities and landowners. The proposal also contains amendments that provide clarity and balance to the mining sector, including the possibility to apply for the immediate enforcement of first-time exploration permits.

The preliminary proposal will be subject to a public hearing in September 2020. After that, the working group heading the amendment process will prepare a legislative proposal that will be considered by Parliament.

EXISTING PRINCIPLES OF FINNISH LAW INCORPORATED INTO THE WORDING OF THE ACT

The proposal includes an amendment to section 6 of the Mining Act (General principles) that aims to ensure the sustainable use of resources by requiring that all minerals that are exploitable from a techno-economic perspective be exploited at one time. Changes that will provide additional clarity to the mining sector include a new section on advice to the applicant (section 31a) and a modification to the section governing amendments of applications (section 36). The new section on advice would grant applicants the right to request guidance from the governing authority; the amendment of section 36 would obligate the competent authority to provide reasoning for requiring additional information. Both amendments reflect guiding principles in Finnish administrative law; they would now be explicitly expressed in the Mining Act as well.

CHANGES TO EXPLORATION ACTIVITIES AND TO GRANTING AND RENEWALS OF PERMITS

From an exploration perspective, the proposal contains amendments to the reservation notification: the reservation period may be shortened to 12 months (a 24-month reservation period can still be granted in special circumstances). Applicants of exploration permits would be granted the right to seek immediate enforcement also for first-time applications.

As regards the renewals of exploration permits, the applicant would have to show that the explorer has completed the exploration activities presented in the previous exploration plan in material respects. Furthermore, if the permit to be renewed has been in force for at least 10 years, the renewal would require approval from at least one-third of the landowners or landholders. If the approval cannot be obtained, the Ministry of the Employment and the Economy may still grant the renewal provided that certain criteria are fulfilled; these include a public need for the project, local and regional employment and community need for the resource to be extracted. 

Clarifications are also expected to the requirements set out for the applicant in the Mining Act, including the requirement of knowledge of the activities to be carried out. These requirements are carried over when a permit is transferred, to ensure that permits are not transferred to parties that do not have adequate knowledge or resources to handle the activities.

Section 48 on the impediments to granting of a mining permit will also be amended so that a mining permit may not be granted for activities that would substantially weaken either the living conditions or the industrial conditions of the locality even if the other conditions are fulfilled; previously, the weakening of both living conditions and industrial conditions was required.

PUBLIC DISCUSSION ON MINING REFLECTED IN THE PROPOSAL

The rights of the municipalities, in turn, are clarified by including a specification that mining will require either a local master plan or a local detailed plan. Pursuant to the Land Use and Building Act (132/1999), which is also being amended by this Government, municipalities have a monopoly on drafting local master plans and local detailed plans.

The proposal includes an overhaul of the collateral system and a requirement to plan the mine so that it can be closed down in sections. This follows a wide public discussion in Finland about the need to ensure sufficient funds for the closure of the mine and for unforeseen events should the mine operator become insolvent. The general opinion is that the costs arising from such events should not be borne by the government or taxpayers. Nonetheless, the legislator should make sure that the collateral provisions in the forthcoming government proposal are aligned with those of the Environmental Protection Act.

As a further response to the public concern, section 156 of the Mining Act governing the rectification of an offence or neglect is sharpened so that the mining authority must act if an offence or neglect is discovered. 

MINING PERMIT AND ENVIRONMENTAL PERMIT CONTINUE TO OVERLAP

Overall, the proposal leaves many things open, with several of the amendments to be clarified by decrees. One of the aims of the Government Program was to improve the consolidation between the mining permit and the environmental permit, which is also required for the operation of a mine. However, the proposal would further blur the line between the two without providing much clarity on how the two permits granted by different authorities should coexist.

Latest references

We advised eQ Community Properties Fund in its acquisition of a property portfolio comprising a health centre in Espoo, a daycare property in Vantaa, an elementary school in Helsinki, and a parking facility property in Helsinki from Ilmarinen Mutual Pension Insurance Company. The lettable area of the first three properties is approximately 13,900 sq.m., while the parking facility offers 120 parking spaces. The portfolio’s tenants include the City of Helsinki, the City of Vantaa, the Western Uusimaa Wellbeing Services County, and Aimo Park Oy. In connection with the transaction, Ilmarinen invested in eQ Community Properties fund as per 31 December 2024.
Case published 9.1.2025
We successfully represented a Finnish manufacturing company in arbitration proceedings under the SCC rules against a global construction company. The dispute was governed by Finnish law and the seat of arbitration was Stockholm, Sweden. The dispute mainly concerned the termination of an erection contract and the right to compensation for delays of the project and for cost increases due to Russia’s invasion of Ukraine. The main questions in dispute were the lawfulness of the termination of the erection contract as well as the consequences of the termination such as the right to costs to complete the project after termination, the right to liquidated damages for delay of the project and adjustment of contract price due to cost increases. The total value of the dispute exceeded EUR 15 million.
Case published 8.1.2025
We advised Korkia Oy in its loan agreement with Nordic Environment Finance Corporation. The financing will support the development and international scale-up of Korkia’s pipeline of solar energy, battery energy storage system (BESS) and onshore wind projects. Korkia is a dedicated investor in renewable energy operating in nine countries. It has a robust development pipeline of over 20 GW in renewable energy and energy storage projects.
Case published 7.1.2025
We acted as the Finnish law legal advisor to Commerzbank AG, which served as the coordinator, bookrunner, documentation agent, facility agent and security agent of an international banking syndicate. This syndicate provided an ECA-covered construction financing facility of more than EUR 1 billion for the Finnish shipyard company Meyer Turku Oy. The loan facility will be used on the construction of one new passenger cruise ship. The newbuilding is the third of the ICON class. According to Meyer Turku Oy the ICON-class ships are the world’s most advanced and the most environmentally friendly cruise ships of their owner, Royal Caribbean Cruise Lines.
Case published 30.12.2024