14.4.2016

Concurrent Delays in International Construction Projects – a Finnish Law Point of View

My previous post on legal transplants covered endeavours clauses. In this article, I am addressing concurrent delays, which is another interesting topic from the perspective of international construction projects.

Concurrent Delay – The Phenomenon

Delays in general are a tricky business. As opposed to other types of contractual changes, such as variations, delays always imply negative consequences. These consequences are imposed on either the employer or the contractor of the project, depending on which is responsible for causing the delay. It is safe to say that neither party welcomes these consequences with open arms, but will rather try to avoid them at all cost. This being the case, delays usually carry the risk of conflict with them.

The risk of conflict tends to increase in the event of concurrent delays. A concurrent delay means a delay that has been caused by two or more events or circumstances at the same time. Even without one of these events, the delay would still have materialised. The problem with concurrent delay arises if both the employer and the contractor are each (at least partially) responsible for one of the events causing delay. 

An example of this would be a scenario where (1) the employer delays the review process of critical design documents (or delivery process of the same, depending on the type of project) and, meanwhile, (2) the contractor performs repairs on deficiently performed works, whilst (3) both of these actions affect the critical path of the project and delay its completion, events or circumstances at the same time. Even without one of these events, the delay would still have materialised. The problem with concurrent delay arises if both the employer and the contractor are each (at least partially) responsible for one of the events causing delay.

Does the contractor get an extension of time for the concurrent part of the delay despite the fact that, even without the employer’s delay, the project would have suffered an equal delay that the contractor is responsible for?

Concurrent Delays under English and Finnish Law

Unless the construction contract specifically addresses concurrent delays, the issue is subject to contractual interpretation. Under common law, there are at least two alternative approaches for handling concurrency (see link below): the ‘Malmaison Approach’ leans towards the contractor being granted an extension of time, whereas the  ‘Apportionment Approach’ implies that the responsibility for the delay could be apportioned between the two causes.

English courts have generally adopted the Malmaison Approach, and so under English law, unless otherwise agreed in the contract, the contractor would be granted an extension of time despite concurrency.

Under Finnish law, ultimately, the effect of concurrency will depend on the contract. The problem is that the wording can be very ambiguous as to concurrency. If the contract states that the Contractor shall be entitled to an extension of time if and to the extent that completion of the works is or will be delayed by acts of the Employer, the relevant question is has the completion in fact been delayed by the acts of the Employer considering that the same delay would have materialised independent of the Employer’s delay.

Practical Considerations

It is worth noting that ‘real’ concurrent delays are, in fact, quite rare. Sometimes, events only seem concurrent, because the programme (detailed schedule of the works) is not sufficient for verifying the actual critical path and the impact of each delay event on said critical path. This is important to keep in mind, since after all, in most large scale projects, it is not the delay as such that entitles the contractor to an extension of time; only delays to the completion of the project are relevant in this context.

In these circumstances, the question of concurrency could be avoided by both parties paying sufficient attention to drafting the programme initially and then keeping it up to date during the project execution. It may show that only one of the delays affected completion.

Concluding Remarks

Since delays in general tend to be a rather volatile topic, there is really no magic wording which would eliminate all risk of disputes relating to delays in a construction project. A good starting point, however, is to specify in the contract – and, importantly, to do so unambiguously – how concurrent delays are to be resolved, along with drafting a sufficiently detailed programme and keeping it mutually up to date at all times.

The programme should show the current critical path at any given time, all dependencies between the various phases of execution (also for those phases that are not on the critical path at that particular time), and the float included in the programme. This way, upon each delay causing event, the programme can be updated without unnecessary argumentation as to, for instance, the alternative chain of dependencies that form the new critical path as a result of the delay.

For common law discussion, see e.g.:
http://www.elexica.com/en/legal-topics/construction/16-concurrent-delays-in-construction-projects

 

Latest references

We advised the urban developer and construction company YIT on the drafting and negotiation of two construction agreements with the leading algorithmic trading firm XTX Markets for the development of two data centres in Kajaani, Finland, which are part of XTX Markets’ data centre complex. The first agreement, valued at approximately EUR 100 million and signed in December 2024, marked the commencement of the construction of the first data centre facility in Kajaani, establishing Kajaani as a strategic hub for high-performance computing infrastructure.  Building on the success of this collaboration, YIT and XTX Markets entered into a second agreement in August 2025 to commence construction of a second data centre facility. This phase includes the delivery of the shell and core of the new building.
Case published 20.11.2025
We assisted Oomi Oy in its expansion into the mobile telecommunications market with the launch of Oomi Mobiili, a new MVNO brand. Our work covered the preceding due diligence process as well as structuring and negotiating key partner agreements, laying a solid foundation for Oomi’s entry into the new market. Oomi Mobiili will operate as a virtual mobile network operator, offering customers the option to purchase a mobile subscription together with their electricity contract. The phased launch is set to begin in autumn 2025, with nationwide availability targeted for early 2026. 
Case published 15.8.2025
Castrén & Snellman is acting as the legal advisor to the City of Pori in its sale of a 49% stake in Pori Energia to Polhem Infra. Pori Energia, a multi-utility company, operates in various sectors including district heating, electricity distribution, and electricity generation through CHP and renewable sources. The company also provides wind power services and industrial energy solutions in the Satakunta region. This strategic partnership between the City of Pori and Polhem Infra aims to enhance Pori Energia’s financial stability and investment capabilities, enabling the company to further its efforts in the energy transition and continue delivering high-quality energy services to its customers. Polhem Infra, owned by Swedish state pension funds, focuses on investments in critical infrastructure, including renewable electricity generation, energy storage, energy distribution, digital infrastructure, and transport infrastructure. The transaction values Pori Energia at EUR 905 million. 
Case published 31.1.2025
We successfully represented a Finnish manufacturing company in arbitration proceedings under the SCC rules against a global construction company. The dispute was governed by Finnish law and the seat of arbitration was Stockholm, Sweden. The dispute mainly concerned the termination of an erection contract and the right to compensation for delays of the project and for cost increases due to Russia’s invasion of Ukraine. The main questions in dispute were the lawfulness of the termination of the erection contract as well as the consequences of the termination such as the right to costs to complete the project after termination, the right to liquidated damages for delay of the project and adjustment of contract price due to cost increases. The total value of the dispute exceeded EUR 15 million.
Case published 8.1.2025