11.5.2020

FinnHEMS – Set-Aside Proceedings of an Arbitral Award

We represented FinnHEMS Oy, the company in charge of Helicopter Emergency Medical Services (HEMS) operations in Finland, in set-aside proceedings.

In 2016, an arbitral tribunal rendered an award dismissing the claims presented by FinnHEMS against one of its service providers. The arbitral tribunal accepted that the service provider had breached the agreement, but decided not to award any compensation to FinnHEMS, as the arbitral tribunal considered FinnHEMS to have failed to give notice of the breaches within a reasonable time. However, the service provider had not invoked failure to give notice as grounds for disputing the claim during the arbitration. Consequently, FinnHEMS initiated set-aside proceedings in the District Court of Helsinki.

The District Court of Helsinki accepted FinnHEMS’ action and set the award aside. The service provider appealed to the Helsinki Court of Appeal, which also found in favour of FinnHEMS. Both the District Court of Helsinki and the Helsinki Court of Appeal accepted FinnHEMS’ argument that the arbitral tribunal had failed to provide FinnHEMS with sufficient opportunity to present its case and had exceeded its jurisdiction when basing its award on grounds not invoked by the parties in the arbitration. The Supreme Court did not grant the service provider leave of appeal, making the decision by the Helsinki Court of Appeal final. 

The threshold for a court to set aside an award is high. Arbitral awards are meant to be final and can only be challenged on very limited grounds. All in all, there is very little legal praxis available relating to set-aside proceedings and even less so where an arbitral award has actually been set aside. Nevertheless, FinnHEMS was able to show that the arbitral tribunal had exceeded its jurisdiction and failed to provide FinnHEMS with sufficient opportunity to present its case to such a degree that the arbitral award was set aside. The final decision by the Helsinki Court of Appeal is noteworthy and rare in Finland and provides good guidance for future cases with respect to the limits of the powers of arbitral tribunals.

Latest references

We advised Delta Capacity AG in a project financing of two battery energy storage systems (BESS). The financed projects are among the largest BESS developments in Finland to enter construction with 250 MW / 600 MWh combined capacity. The financing was provided by Société Générale with support from Finnvera. Construction of both projects, located in Lapinlahti and Teuva, has already begun and the commercial operations are targeted to commence in late 2027 with partial tolling agreements already in place for both assets. The project in Lapinlahti is executed in partnership with Covenergo, while the project in Teuva is executed in partnership with Strioga Family Foundation. Delta Capacity is a Swiss developer of utility-scale battery storage systems. The projects strengthen Delta Capacity’s growing Nordic portfolio and support the flexibility of Finland’s electricity system by adding energy storage capacity, enabling production optimization as well as participation in electricity markets and reserve services.
Case published 28.10.2026
We acted as Finnish legal advisor to Delta Capacity in connection with its acquisition of the ready-to-build Karppio battery energy storage system (BESS) project from Helios Nordic Energy. The acquisition was made and the project will be implemented together with Strioga Family Foundation. The Karppio BESS project is located in Teuva, Finland, and has a capacity of 125 MW / 300 MWh. Delta Capacity will lead the remaining development of the project through to commissioning, planned for 2027, and will serve as long-term asset manager. Delta Capacity is a Swiss-based developer of utility scale battery storage systems. The acquisition adds to Delta Capacity’s growing Nordic portfolio. 
Case published 20.7.2026
We advised Oomi Solar Oy on the sale of a solar power park and battery energy storage project to Tuulipolar Oy. The transaction concerned a 24 MWp solar power plant and a 36 MW / 70 MWh battery energy storage system (BESS) to be constructed in Tornio. Tuulipolar Oy will act as the owner and operator of the plant, while Oomi Solar Oy will be responsible for its design and construction. The project will form the world’s northernmost industrial hybrid power plant, contributing to Finland’s green energy transition by increasing renewable energy production and electricity storage capacity in Northern Finland. The hybrid solution enables optimization of production as well as active participation in electricity markets and reserve services, improving the project’s profitability and supporting the balance of the electricity system year-round. Electricity production from the hybrid plant is expected to begin in 2028. Oomi Solar Oy is a Finnish renewable energy expert with experience from nearly 200 MW of installed solar capacity. The company helps businesses and communities accelerate the green transition by offering comprehensive solutions, including solar power plants, energy storage systems, and related lifecycle services from project development to maintenance. Oomi Solar Oy employs more than 20 energy professionals and delivers solar power projects across Finland. The company’s vision is to be Finland’s most desired partner for solar energy and energy solutions.
Case published 5.6.2026
Castrén & Snellman advised Nscale, a European AI infrastructure company, in connection with its planned data centre project in Harjavalta, Finland. The facility will be located in the Sievari industrial area. Castrén & Snellman’s advisory role encompassed the negotiation and execution of a site securing and development agreement (SSDA) with Fortum, as well as the preliminary land sale process for the Sievari site with the Town of Harjavalta. Under the SSDA, Fortum supports the advancement of Nscale’s project development, including grid connection design and permitting.
Case published 15.4.2026